Once we have created the WBS, the next step is to develop the Project Schedule.
The easiest way to remember it is:
WBS tells us WHAT work has to be done. Schedule tells us WHEN and in WHAT ORDER the work will be done.
1. What is a Project Schedule?
A project schedule is a plan that shows:
- What activities have to be performed
- When each activity will start
- When it will finish
- How long it will take
- Which activities depend on others
- Who/resources may be required
Exam definition
A project schedule is a time-based plan that defines project activities, their sequence, duration, start and finish dates, dependencies and resources required to complete the project.
2. Why Do We Need a Project Schedule?
Suppose we are developing an Online Shopping Website.
We cannot randomly start activities.
For example:
❌ We cannot properly test the software before development is completed.
❌ We cannot start coding without knowing what needs to be developed.
Therefore, activities need to be arranged in the correct order.
A schedule helps us determine:
What → When → How long → In what order → Using which resources
3. Developing a Project Schedule
The basic process is:
Create WBS
↓
Identify Activities
↓
Sequence Activities
↓
Estimate Activity Duration
↓
Estimate Resources
↓
Develop Schedule
↓
Analyze Critical Path
↓
Approve Schedule
↓
Monitor & Update Schedule
Let’s understand each step.
4. Step 1 — Start with WBS
The WBS tells us the major work required.
Example:
E-Commerce Website
│
├── Requirements
├── Design
├── Development
├── Testing
└── Deployment
We now convert these components into activities.
5. Step 2 — Identify Activities
Break work packages into activities that must actually be performed.
For example:
Design
- Design database
- Design user interface
- Design system architecture
Development
- Develop login
- Develop product module
- Develop shopping cart
- Develop payment system
Testing
- Unit testing
- Integration testing
- System testing
6. Step 3 — Sequence the Activities
Now determine which activity comes first and which comes later.
Example:
Requirements
↓
System Design
↓
Development
↓
Testing
↓
Deployment
Why?
Because testing cannot properly begin until the software is developed.
7. Activity Dependencies
A dependency means that one activity depends on another activity.
Example
A → B
means:
Activity B depends on Activity A.
For example:
Design → Development
Development depends on completion of the design.
8. Four Common Types of Dependencies
These are important for exams.
1. Finish-to-Start (FS)
The first activity must finish before the second activity starts.
Example:
Design must finish before coding starts.
Design ───────→ Development
Finish Start
This is the most common dependency.
2. Start-to-Start (SS)
The second activity can start after the first activity starts.
Example:
Development of two modules can start after overall development begins.
Activity A ──────→
Start
↓
Activity B ──────→
Start
3. Finish-to-Finish (FF)
One activity cannot finish until another activity finishes.
Example:
Two testing activities need to finish around the same stage.
Activity A ──────→ Finish
↓
Activity B ──────→ Finish
4. Start-to-Finish (SF)
The second activity cannot finish until the first activity starts.
This is rarely used.
Example:
A night support team may continue working until the morning support team starts.
New Shift
Start
↓
Old Shift ───────── Finish
Memory trick:
FS = Finish → Start
SS = Start → Start
FF = Finish → Finish
SF = Start → Finish
9. Step 4 — Estimate Activity Duration
Now determine:
How much time will each activity take?
Example:
| Activity | Duration |
|---|---|
| Requirements | 5 days |
| Design | 8 days |
| Development | 20 days |
| Testing | 10 days |
| Deployment | 2 days |
Duration can depend on:
- Complexity
- Number of resources
- Skills of team
- Technology
- Historical data
- Availability of resources
10. Step 5 — Estimate Resources
Determine what resources are required for each activity.
Resources may include:
- Developers
- Testers
- Designers
- Hardware
- Software
- Servers
- Budget
Example:
| Activity | Resource |
|---|---|
| UI Design | UI Designer |
| Coding | Developers |
| Testing | Testers |
| Deployment | DevOps Engineer |
11. Step 6 — Develop the Schedule
Now combine:
Activities + Dependencies + Duration + Resources
to create the actual schedule.
Example:
| Activity | Duration | Predecessor |
|---|---|---|
| Requirements | 5 days | — |
| Design | 8 days | Requirements |
| Development | 20 days | Design |
| Testing | 10 days | Development |
| Deployment | 2 days | Testing |
This gives us the sequence of work.
12. Gantt Chart
One of the most common ways to represent a project schedule is a Gantt Chart.
A Gantt chart shows activities against time.
Example
Activity Week 1 2 3 4 5 6 7 8
------------------------------------------------
Requirements ███
Design ███
Development █████████
Testing █████
Deployment ██
It provides a visual representation of:
- Start date
- End date
- Duration
- Progress
Advantages
It is easy to understand and useful for communicating project progress.
13. Network Diagram
Another important scheduling technique is a Network Diagram.
It shows the logical relationships between activities.
Example:
A
Requirements
↓
B
Design
↓
C
Development
↓
D
Testing
↓
E
Deployment
Network diagrams are particularly useful for:
- Dependency analysis
- Critical Path Analysis
- PERT
- Project duration calculation
14. Critical Path
While developing a schedule, we need to identify the Critical Path.
Simple definition:
Critical Path is the longest sequence of dependent activities in a project network that determines the minimum possible project completion time.
Important point:
Activities on the critical path generally have:
Zero total float/slack.
If a critical-path activity is delayed, the entire project may be delayed unless corrective action is taken.
Example
Suppose:
A = 5 days
B = 8 days
C = 10 days
and:
A → B → C
Then project duration:
5 + 8 + 10 = 23 days
If this is the longest path, it is the critical path.
We will study Critical Path Analysis separately in detail later in your syllabus.
15. Schedule Baseline
Once the schedule is reviewed and approved, it can become a schedule baseline.
The baseline is the approved version against which actual progress is compared.
Example:
Planned
Testing: 1–10 March
Actual
Testing: 4–15 March
The project manager can compare actual performance with the baseline and identify the delay.
16. Schedule Compression
Sometimes a project needs to be completed faster than originally planned.
Two important techniques are:
1. Crashing
Add more resources to reduce duration.
Example:
Instead of:
2 developers → 20 days
Use:
4 developers → potentially shorter duration
But this may increase cost.
2. Fast Tracking
Perform activities in parallel that were originally planned sequentially, where technically possible.
Example:
Instead of:
Design → Development
some development may start while design is still being completed.
But this increases risk and rework.
These techniques will be covered in more detail later under Effect of Schedule Compression.
17. Example — Complete Project Schedule
Suppose we are developing a College Management System.
| ID | Activity | Duration | Predecessor |
|---|---|---|---|
| A | Requirements | 5 days | — |
| B | System Design | 7 days | A |
| C | Database Design | 5 days | B |
| D | Coding | 15 days | C |
| E | Testing | 8 days | D |
| F | Deployment | 2 days | E |
The logical flow is:
A
Requirements
↓
B
System Design
↓
C
Database Design
↓
D
Coding
↓
E
Testing
↓
F
Deployment
If these activities are sequential, total duration is:
5 + 7 + 5 + 15 + 8 + 2 = 42 days
So the project requires 42 working days, assuming no overlap and no other constraints.
18. Important Difference: WBS vs Schedule
| WBS | Project Schedule |
|---|---|
| Defines project work | Defines timing of work |
| Answers What? | Answers When? |
| Hierarchical structure | Time-based plan |
| Identifies work packages | Identifies activities and dates |
| Foundation for scheduling | Uses WBS as input |
| Does not primarily show timing | Shows start/end and duration |
Remember:
WBS = WHAT
Schedule = WHEN
Network = IN WHAT ORDER
Critical Path = WHAT DETERMINES PROJECT DURATION
⭐ Exam-Oriented Answer
Q. Explain the process of developing a project schedule.
Answer:
Project scheduling is the process of identifying project activities, determining their sequence and dependencies, estimating their duration and resources, and developing a time-based plan for completing the project.
Steps:
- Create WBS
- Identify project activities
- Sequence activities
- Determine dependencies
- Estimate activity durations
- Estimate required resources
- Develop the project schedule
- Analyze critical path
- Establish schedule baseline
- Monitor and update the schedule
Main scheduling tools:
- Gantt Chart
- Network Diagram
- Critical Path Method (CPM)
- PERT
🧠 Easy Memory Formula
Remember:
WBS → Activities → Sequence → Duration → Resources → Schedule → Critical Path
This is the complete logic of Developing the Project Schedule.
The next topic in your syllabus is Developing the Project Cost Estimate, where we will learn how to calculate the expected cost of the project.
