Home » Developing the Project Schedule

Developing the Project Schedule

Once we have created the WBS, the next step is to develop the Project Schedule.

The easiest way to remember it is:

WBS tells us WHAT work has to be done. Schedule tells us WHEN and in WHAT ORDER the work will be done.


1. What is a Project Schedule?

A project schedule is a plan that shows:

  • What activities have to be performed
  • When each activity will start
  • When it will finish
  • How long it will take
  • Which activities depend on others
  • Who/resources may be required

Exam definition

A project schedule is a time-based plan that defines project activities, their sequence, duration, start and finish dates, dependencies and resources required to complete the project.


2. Why Do We Need a Project Schedule?

Suppose we are developing an Online Shopping Website.

We cannot randomly start activities.

For example:

❌ We cannot properly test the software before development is completed.

❌ We cannot start coding without knowing what needs to be developed.

Therefore, activities need to be arranged in the correct order.

A schedule helps us determine:

What → When → How long → In what order → Using which resources


3. Developing a Project Schedule

The basic process is:

Create WBS
    ↓
Identify Activities
    ↓
Sequence Activities
    ↓
Estimate Activity Duration
    ↓
Estimate Resources
    ↓
Develop Schedule
    ↓
Analyze Critical Path
    ↓
Approve Schedule
    ↓
Monitor & Update Schedule

Let’s understand each step.


4. Step 1 — Start with WBS

The WBS tells us the major work required.

Example:

E-Commerce Website
│
├── Requirements
├── Design
├── Development
├── Testing
└── Deployment

We now convert these components into activities.


5. Step 2 — Identify Activities

Break work packages into activities that must actually be performed.

For example:

Design

  • Design database
  • Design user interface
  • Design system architecture

Development

  • Develop login
  • Develop product module
  • Develop shopping cart
  • Develop payment system

Testing

  • Unit testing
  • Integration testing
  • System testing

6. Step 3 — Sequence the Activities

Now determine which activity comes first and which comes later.

Example:

Requirements
     ↓
System Design
     ↓
Development
     ↓
Testing
     ↓
Deployment

Why?

Because testing cannot properly begin until the software is developed.


7. Activity Dependencies

A dependency means that one activity depends on another activity.

Example

A → B

means:

Activity B depends on Activity A.

For example:

Design → Development

Development depends on completion of the design.


8. Four Common Types of Dependencies

These are important for exams.

1. Finish-to-Start (FS)

The first activity must finish before the second activity starts.

Example:

Design must finish before coding starts.

Design ───────→ Development
 Finish          Start

This is the most common dependency.


2. Start-to-Start (SS)

The second activity can start after the first activity starts.

Example:

Development of two modules can start after overall development begins.

Activity A ──────→
       Start
          ↓
Activity B ──────→
       Start

3. Finish-to-Finish (FF)

One activity cannot finish until another activity finishes.

Example:

Two testing activities need to finish around the same stage.

Activity A ──────→ Finish
                      ↓
Activity B ──────→ Finish

4. Start-to-Finish (SF)

The second activity cannot finish until the first activity starts.

This is rarely used.

Example:

A night support team may continue working until the morning support team starts.

New Shift
   Start
     ↓
Old Shift ───────── Finish

Memory trick:

FS = Finish → Start

SS = Start → Start

FF = Finish → Finish

SF = Start → Finish


9. Step 4 — Estimate Activity Duration

Now determine:

How much time will each activity take?

Example:

ActivityDuration
Requirements5 days
Design8 days
Development20 days
Testing10 days
Deployment2 days

Duration can depend on:

  • Complexity
  • Number of resources
  • Skills of team
  • Technology
  • Historical data
  • Availability of resources

10. Step 5 — Estimate Resources

Determine what resources are required for each activity.

Resources may include:

  • Developers
  • Testers
  • Designers
  • Hardware
  • Software
  • Servers
  • Budget

Example:

ActivityResource
UI DesignUI Designer
CodingDevelopers
TestingTesters
DeploymentDevOps Engineer

11. Step 6 — Develop the Schedule

Now combine:

Activities + Dependencies + Duration + Resources

to create the actual schedule.

Example:

ActivityDurationPredecessor
Requirements5 days—
Design8 daysRequirements
Development20 daysDesign
Testing10 daysDevelopment
Deployment2 daysTesting

This gives us the sequence of work.


12. Gantt Chart

One of the most common ways to represent a project schedule is a Gantt Chart.

A Gantt chart shows activities against time.

Example

Activity       Week 1  2  3  4  5  6  7  8
------------------------------------------------
Requirements   ███
Design            ███
Development          █████████
Testing                       █████
Deployment                         ██

It provides a visual representation of:

  • Start date
  • End date
  • Duration
  • Progress

Advantages

It is easy to understand and useful for communicating project progress.


13. Network Diagram

Another important scheduling technique is a Network Diagram.

It shows the logical relationships between activities.

Example:

        A
     Requirements
          ↓
          B
        Design
          ↓
          C
     Development
          ↓
          D
       Testing
          ↓
          E
      Deployment

Network diagrams are particularly useful for:

  • Dependency analysis
  • Critical Path Analysis
  • PERT
  • Project duration calculation

14. Critical Path

While developing a schedule, we need to identify the Critical Path.

Simple definition:

Critical Path is the longest sequence of dependent activities in a project network that determines the minimum possible project completion time.

Important point:

Activities on the critical path generally have:

Zero total float/slack.

If a critical-path activity is delayed, the entire project may be delayed unless corrective action is taken.

Example

Suppose:

A = 5 days
B = 8 days
C = 10 days

and:

A → B → C

Then project duration:

5 + 8 + 10 = 23 days

If this is the longest path, it is the critical path.

We will study Critical Path Analysis separately in detail later in your syllabus.


15. Schedule Baseline

Once the schedule is reviewed and approved, it can become a schedule baseline.

The baseline is the approved version against which actual progress is compared.

Example:

Planned

Testing: 1–10 March

Actual

Testing: 4–15 March

The project manager can compare actual performance with the baseline and identify the delay.


16. Schedule Compression

Sometimes a project needs to be completed faster than originally planned.

Two important techniques are:

1. Crashing

Add more resources to reduce duration.

Example:

Instead of:

2 developers → 20 days

Use:

4 developers → potentially shorter duration

But this may increase cost.

2. Fast Tracking

Perform activities in parallel that were originally planned sequentially, where technically possible.

Example:

Instead of:

Design → Development

some development may start while design is still being completed.

But this increases risk and rework.

These techniques will be covered in more detail later under Effect of Schedule Compression.


17. Example — Complete Project Schedule

Suppose we are developing a College Management System.

IDActivityDurationPredecessor
ARequirements5 days—
BSystem Design7 daysA
CDatabase Design5 daysB
DCoding15 daysC
ETesting8 daysD
FDeployment2 daysE

The logical flow is:

A
Requirements
   ↓
B
System Design
   ↓
C
Database Design
   ↓
D
Coding
   ↓
E
Testing
   ↓
F
Deployment

If these activities are sequential, total duration is:

5 + 7 + 5 + 15 + 8 + 2 = 42 days

So the project requires 42 working days, assuming no overlap and no other constraints.


18. Important Difference: WBS vs Schedule

WBSProject Schedule
Defines project workDefines timing of work
Answers What?Answers When?
Hierarchical structureTime-based plan
Identifies work packagesIdentifies activities and dates
Foundation for schedulingUses WBS as input
Does not primarily show timingShows start/end and duration

Remember:

WBS = WHAT

Schedule = WHEN

Network = IN WHAT ORDER

Critical Path = WHAT DETERMINES PROJECT DURATION


⭐ Exam-Oriented Answer

Q. Explain the process of developing a project schedule.

Answer:

Project scheduling is the process of identifying project activities, determining their sequence and dependencies, estimating their duration and resources, and developing a time-based plan for completing the project.

Steps:

  1. Create WBS
  2. Identify project activities
  3. Sequence activities
  4. Determine dependencies
  5. Estimate activity durations
  6. Estimate required resources
  7. Develop the project schedule
  8. Analyze critical path
  9. Establish schedule baseline
  10. Monitor and update the schedule

Main scheduling tools:

  • Gantt Chart
  • Network Diagram
  • Critical Path Method (CPM)
  • PERT

🧠 Easy Memory Formula

Remember:

WBS → Activities → Sequence → Duration → Resources → Schedule → Critical Path

This is the complete logic of Developing the Project Schedule.